The Karczemki junction is the largest road junction in northern Poland. Its expansion is one of the most important road projects in Gdańsk in 2012. The investment provides a free connection between the city centre and the Tri-City ring road, where all relations and the route of the journey take place in a collision-free manner.
As a result of the settlement of the road body, a surface failure occurred at the section of the Żukowo - Gdańsk exit.
INGEO Sp. z o. o. carried out an expert study in order to identify the probable cause of incorrect functioning of the road and carried out a technological project to eliminate the breakdown of the road body on the section of the Żukowo-Gdynia exit at the Karczemki interchange in Gdańsk. The study was commissioned by BUDIMEX S. A.
We have prepared a report on soil tests in the area of failure, and as part of the solution to the problem we have designed the reconstruction work of the road body and the execution of additional soil reinforcement.
In September 2010, INGEO Sp. z o. o. carried out geological surveys of the substrate for the investment of the extension of the Karczemki Node in Gdańsk and prepared geotechnical documentation from the land survey to determine the soil and water conditions in the area of the planned reconstruction from the Jasień Lake side.